Work package summary
Start date: | 2 June 2014 |
End date: | 19 September 2014 |
Revised, since the deliverable of work package 2 forms an appropriate interim report.
Description
Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in work package 1, work package 2 and work package 3.
Deliverables
A report as described, with the deliverable of work package 2 forming the interim report, to be delivered by 25 July 2014.
Dependencies
Ran concurrently with work package 1, work package 2 and work package 3.
Status
Complete.
Approach
Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in WP1, WP2 and WP3.
Notes
This will provide an extended version of the WP2 deliverable.
Deliverables
Available: final technical report