Difference between revisions of "Work Package 4"

From Superoptimization
Jump to: navigation, search
(Deliverables)
(Notes)
 
Line 31: Line 31:
 
Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in WP1, WP2 and WP3.
 
Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in WP1, WP2 and WP3.
 
== Notes ==
 
== Notes ==
This will provide an extended version of the WP2 deliverable.
+
 
 +
This provided an extended version of the WP2 deliverable.
  
 
== Deliverables ==
 
== Deliverables ==
 
Available: [[Final report|final technical report]]
 
Available: [[Final report|final technical report]]

Latest revision as of 16:09, 20 October 2014

Work package summary

Start date: 2 June 2014
End date: 19 September 2014

Revised, since the deliverable of work package 2 forms an appropriate interim report.

Description

Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in work package 1, work package 2 and work package 3.

Deliverables

A report as described, with the deliverable of work package 2 formed the interim report, and was delivered on 1 August 2014.

The final technical report was delivered on 30 September 2014.

Dependencies

Ran concurrently with work package 1, work package 2 and work package 3.

Status

Complete.

Approach

Document the generalized process to demonstrate repeatability. This is the main engineering documentation of the project, and should provide sufficient information to guide a future product implementation. This will include appropriate reference to the work in WP1, WP2 and WP3.

Notes

This provided an extended version of the WP2 deliverable.

Deliverables

Available: final technical report